Can I get a work load view for all People at once?

When I go into the People tab, the Calendar view is inactive. Is there a possibility to view all employees in one Gantt chart so that I can see who has a spare day here or there?

thanks,

 Nick

3 comments

  • 0
    Avatar
    Ben Hadden

    Hi Nick,

    The "Calendar View" option on a page shows all Tasks linked to things on that page, so it would show Tasks linked to People (not "Assigned To"), but I totally see what you're after.  Right now, there isn't an excellent way to show a list of your People with their Tasks alongside them--the best way to do this is to look at your main Schedule page and group by "Assigned To".  Another method that works well is to create a query field on People that shows a count of all the Tasks assigned to each Person.

    We're working on a larger "resource planner" feature that will address this issue, which we hope to have by early next year.  In the meantime, I'm happy to brainstorm with you on ways around this.  Let me know if either of the above two options sounds like it'd work.

  • 0
    Avatar
    Adam Chrystie

    Hi Ben,

     

        My production team has the same request. Is the resource planner done or should i go with the above methodology? Thanks for any info.

  • 0
    Avatar
    Adam Chrystie

    Hi Ben,

     

        My production team has the same request. Is the resource planner done or should i go with the above methodology? Thanks for any info.