External Dependencies

Is there any way to specify a dependency from outside the current entity?

The simplest example would be I have 2 scenes and I want a task from Scene A to be a dependency on a task in Scene B.

2 comments

  • Avatar
    Tram Le-Jones Official comment

    Hi, Mirza:

    Yes, this is possible though it can get a bit messy.  On a Task page in list view, you want to show all Tasks you want linked. To make it a bit more simple, make a filter for Tasks that are linked to the specific parent entities you want to create a dependency on. Next, make sure they are sorted based on the task that should be upstream, at the top. Select the tasks you want to link, right click and select Dependencies -> link selected.

    Give that a shot and let us know if you have further questions!  You can also write into us at support@shotgunsoftware.com.

    Best,
    Tram

  • 0
    Avatar
    Mirza Baig

    Got it working, thanks!